Surat–Bilimora Section of Bullet Train Corridor Energised, Testing Moves Closer

India's first high-speed rail project achieves a major electrification milestone as the 50-km section prepares for further testing activities.

Surat, November 21, 2026: India’s first Bullet Train project has achieved a significant milestone with the successful energisation of the Overhead Equipment (OHE) system on the Surat–Bilimora section of the Mumbai–Ahmedabad High-Speed Rail corridor on November 20, 2026.

PROJECT MILESTONE

Surat–Bilimora Section Successfully Energised

The development marks an important step towards further testing activities on India’s first high-speed rail corridor.

Energisation will be carried out progressively in smaller sections under the close supervision of technical teams to ensure safety and compliance with prescribed procedures.

 

The section covers both Up and Down lines on the elevated alignment and represents an important advancement in the project’s electrification and testing preparations.

Advanced 2 × 25 kV Traction System

The Mumbai–Ahmedabad Bullet Train corridor is equipped with an advanced 2 × 25 kV Overhead Traction System, one of the sophisticated electrification technologies used in high-speed rail networks worldwide.

The electrification network includes 14 strategically located Traction Substations (TSS) along the 508-km corridor. These substations will receive electricity from the National Grid and supply power to the overhead traction system used by high-speed trains.

Bullet Train Corridor at a Glance

Total corridor length 508 km
Traction substations 14
Traction technology 2 × 25 kV
Surat–Bilimora section Approx. 50 km

Bilimora Traction Substation Completes Key Installations

The first Traction Substation at Bilimora, located in Gujarat’s Navsari district, has completed installation works in its Control Panel, Changeover Switch, Transformer and Circuit Breaker buildings.

The Traction Substations in Gujarat will receive power from the 220 kV Ambetha Grid Substation of Gujarat Energy Transmission Corporation Limited (GETCO).

The entire electrical network will be monitored through a centralised control centre to ensure safe and reliable operations across the corridor.

50-km Elevated Section Features Four River Bridges

The Surat–Bilimora section comprises approximately 50 km of elevated alignment connecting the two stations. The route includes bridges across four rivers and a steel bridge over National Highway 53 (NH-53).

The viaduct is also equipped with approximately 94,000 noise barriers designed to minimise noise impact on surrounding areas.

PUBLIC SAFETY ADVISORY

Stay Away from Overhead Electrical Installations

Following the energisation of the overhead electrical system, residents, commuters, construction workers and members of the public in the vicinity of the alignment are strictly advised not to approach or touch overhead electrical installations or undertake any unauthorised work near them.

The successful energisation of the Surat–Bilimora section marks another important step in advancing India’s first Bullet Train corridor towards further testing and future operations.